In relation to the tendering of Hesselø Offshore Wind Farm, a range of preliminary investigations and environmental assessments are being carried out.
Results in the form of reports and data from the completed investigations can be accessed directly here at this site (reports) and through access to a FTP site (data), which is maintained by Energinet. All results from the preliminary investigations etc. are targeted potential bidders for Hesselø OWF.
Access to Energinet's FTP site
Access to Energinet’s FTP site is obtained in the following way:
Step 1: Interested bidders can request access to the data by notifying the Danish Energy Agency. Send the request to Randi Lucie Aliaga (rla@ens.dk) or Anders Møller Jørgensen (anmj@ens.dk) and include the following information:
- Applicant name (company name or name of the consortium)
- Applicant’s contact person, (name)
- Applicant’s contact person, (email)
- Applicant’s contact person, (telephone number)
Step 2: Energinet will thus send instructions to the applicant on access to the FTP server with username and password.
The FTP website will be updated for the new site. Reports, which are related to the environment and other reports, which do not require FTP server, will be posted on this page.
New site
Below you can find the list of preliminary investigations to be carried out. There is also an indication of when each report is expected to be published.
Link for list with brief explanatory notes: Preliminary investigation deliveries
Metocean
ID |
Deliverable |
Date |
---|---|---|
2100 |
Measurement Plan |
2023-06-30* |
2102 | Measurements (data) | 2024-09-30* |
2103 | Measurement Reports | 2024-09-30* |
2104 | Site Metocean Conditions Assessment Report | 2024-08-14* |
2105 | Site Wind Conditions Assessment Report | 2024-08-14* |
2106 | Site Ice Conditions Assessment Report | 2024-08-31* |
2107 | Statement of feasibility from Certification Body | 2024-09-30* |
2108 | Reverification note for Site Metocean Conditions Assessment Report | 2025-11-30* |
2109 | Reverification note for Site Wind Conditions Assessment Report | 2025-11-30* |
*Dates are tentative and will be updated when confirmed.
Environmental assessments and permits
ID | Delivery | Date |
---|---|---|
2201 | Scoping of Strategic Environmental Assessment (SEA) for Hesselø OWF (Afgrænsning af miljøvurderingen af planen for Hesselø Havvindmøllepark) |
Published |
2202 | Scoping of Environmental Impact Assessment (EIA) of the land-based project for Hesselø OWF (Udtalelse om afgrænsning af indholdet i miljøkonsekvensrapporten for landanlæg til Hesselø Havvindmøllepark) |
Published |
2203 | Environmental report (SEA) for Hesselø OWF – public consultation (Offentliggørelse af miljørapporten for Hesselø Havvindmøllepark) |
Feb 2024* |
2204 | SEA summary statement (Sammenfattende redegørelse for miljøvurderingen af planen) |
expected feb 2024* |
2205 | EIA report for the land-based project – public consultation | expected feb 2024* |
2206 | EIA permit for land-based project obtained (VVM-tilladelse til landanlæg meddelt) |
expected medio 2024* |
2207 | Planning documents for Hesselø OWF onshore elements Plangrundlag (landsplandirektiv) |
expected medio 2024* |
*Dates are tentative and will be updated when confirmed.
Technical reports and reports on environment
ID | Delivery | Date |
---|---|---|
2208 | Visibility analysis | Feb 2024* |
2209 | Benthic fauna and flora | 2024-12-01* |
2210 | Marine mammals (1 year) | 2024-12-01* |
2212 | Birds (1 year) | 2024-12-01* |
2214 | Bats | 2024-12-01* |
2215 | Fish and fish populations | 2024-12-01* |
2216 | Fisheries | 2024-12-01* |
2217 | Underwater noise and vibrations | 2024-12-01* |
2218 | Radar and radio interference | 2024-12-01* |
2219 | Marine traffic and safety of navigation (HAZID) | 2024-12-01* |
*Dates are tentative and will be updated when confirmed.
Seabed investigations
ID | Delivery | Date |
---|---|---|
2301 | Geology and sea-level, desk study | 2023-08-01 |
2302 | Marine archaeology: Archaeological analysis, desk study | 2023-08-01 |
2303 | Geophysical site survey, report | 2024-07-01 |
2304 | Preliminary geotechnical investigations, report | 2024-07-01 |
2305 | Integrated 3D geological model | 2024-09-01 |
2306 | UXO threat and risk assessment, report | 2023-12-01 |
2307 | Marine archaeology: Geoarchaeological analysis, report | 2024-09-01 |
2308 | Export cables, cable route survey report | 2024-09-01* |
2309 | Export cables, Cable Burial Assessment | 2024-09-01* |
2310 | Export cables, Landfall Site investigations | 2024-09-01* |
*Dates are tentative and will be updated when confirmed.
Old site (Cancelled)
Below you can find the list of all investigations to be carried out, including notes describing the reports. There is also an indication of when each report is expected to be published. Read the notes
ID |
Deliverable |
Date |
Note |
---|---|---|---|
|
|
|
|
100 |
MetOcean |
|
|
101 |
Published |
Note 7 |
|
102 |
Published |
Note 8 |
|
103 |
Reports on Ocean data (Hindcast) Metocean Conditions Assessment
|
Published |
Note 9 |
|
|
|
|
200 |
Environmental assessments and permits |
|
|
201 |
Scoping of strategic environmental assessment (SEA) for Hesselø OWF (Afgrænsningsudtalelse for strategisk miljøvurdering (SMV) af Hesselø Havvindmøllepark) |
Published |
Note 10 |
202 |
Scoping of environmental impact assessment (EIA) of the land-based project for Hesselø OWF (Afgrænsningsudtalelse for miljøvurdering (VVM) af landanlægget til Hesselø Havvindmøllepark) |
Published |
Note 11 |
203 |
Planning consent for extension of Hovegård substation and new Pårup substation approved and made public (Landsplandirektiv for udvidelse af Hovegård højspændingsstation og ny kompenseringsstation ved Pårup vedtaget og publiceret) |
2022 |
Note 12 |
204 |
Environmental Statement/SEA report for plan Hesselø OWF made public (Offentliggørelse af miljørapport (SMV) for planen for Hesselø Havvindmøllepark) |
April 2022 |
Note 13 |
205 |
EIA report for the land-based project submitted and made public (Miljøkonsekvensrapport for landanlæg til Hesselø Havvindmøllepark i høring) |
April 2022 |
Note 14 |
206 |
EIA permit for land-based project obtained (VVM-tilladelse til landanlæg meddelt) |
Mid-2022 |
Note 15 |
207 |
SEA summary statement (Sammenfattende redegørelse for strategisk miljøvurdering (SMV)) |
Mid-2022 |
Note 23 |
|
|
|
|
|
Technical reports and reports on environment |
|
|
208 |
Published Published |
Note 1 |
|
209 |
Published |
Note 16 |
|
210 |
Benthic flora and fauna: Hard bottom - Technical report |
Published |
Note 17 |
211 |
Visualiseringsrapport – Hesselø Havvindmøllepark – eksempelvisualiseringer |
Published |
Note 18 |
212 |
Navigational risk assessment of Hesselø offshore wind farm - Risk Assessment Report |
Published |
Note 19 |
213 |
Published |
Note 20 |
|
214 |
Published |
Note 21 |
|
215 |
Published |
Note 22 |
|
|
|
|
|
300 |
Seabed investigations |
|
|
|
Geophysical survey |
|
|
301 |
Published
|
Note 1 |
|
302 |
Published |
Note 1 |
|
303 |
Published |
Note 2 |
|
304 |
Published |
Note 3 |
|
305 |
Marine Archaeology Geoarkæologisk Analyse – Offshore Wind Farm Geoarkæologisk Analyse OWF - Bilag Geoarkæologisk Analyse – Export Cable Corridor |
Published |
Note 4 |
306 |
UXO risk assessment report Desk study for potential UXO contamination – Hesselø windfarm site Desk study for potential UXO contamination – Hesselø export cable route |
Published |
Note 1 |
|
Geotechnical investigations |
|
|
307 |
Published |
Note 1 |
|
308 |
Published |
Note 5 |
|
309 |
3D geological model reports |
Published |
Note 6 |
310 |
Published |
Note 1 |
|
311 |
Published |
Download GIS files
GIS files for the site of Hesselø OWF (zip) and the export cables towards the landfall at Gilbjerg Hoved (zip)