Great interest in building the Danish Thor Offshore Wind Farm

14. January 2021

The Danish Energy Agency has prequalified a total of six consortia and companies to participate in the tender for Denmark's largest offshore wind farm to date: Thor Offshore Wind Farm with a capacity of minimum 800-1000 MW.

There will be competition to build Denmark's largest offshore wind farm to date, which will be located in the North Sea off the coast at Thorsminde. By 1 December 2020, the Danish Energy Agency received a total of six applications from a broad field of consortia and companies wishing to bid for the task of building the Thor Offshore Wind Farm. All six consortia and companies meet the criteria for financial and technical capacity, and the Agency has prequalified all six of them.

“It is a strong set of players that has applied to be prequalified to bid for building Thor Offshore Wind Farm. This confirms that Denmark remains an attractive country when it comes to investments in offshore wind. Furthermore, the great interest is crucial for a cost-effective green transition” says Deputy Director of the Danish Energy Agency Janni Torp Kjærgaard.

The selected applicants are the following (in alphabetical order):

  1. SSE Renewables Offshore Windfarm Holdings Limited and Thor OFW K/S (owned by Copenhagen Infrastructure IV Thor OFW ApS and Andel Holding A/S) on behalf of a not yet established subsidiary
  2. Swan Wind P/S (ultimately owned by Eneco Wind B.V. and European Energy A/S)
  3. Thor Wind Farm I/S (owned by RWE Wind Holding A/S and RWE Offshore Wind A/S)
  4. Total Renewables S.A.S and Iberdrola Renovables Internacional S.A.U on behalf of a not yet established entity
  5. Vattenfall Vindkraft A/S on behalf of a not yet established entity
  6. Ørsted Wind Power A/S

The Danish Energy Agency will complete the tender during 2021. The decision on the winner of the tender is expected to be announced at the end of 2021.

About Thor

  • Thor Offshore Wind Farm will so far be Denmark's largest and will be located in the North Sea at least 20 km from the coast. Thor Offshore Wind Farm is the first of the three offshore wind farms agreed to be established in the Danish Energy Agreement from 2018.
  • As something new, the park is tendered out with a flexibility of 800-1000 MW, just as the grid connection from the wind farm to the shore is included in the tender.
  • Thor can supply electricity to around 800,000 Danish households. The total investment costs for Thor are estimated at a total of DKK 15.5 billion.
  • The grid connection of the first turbine can take place from 1 January 2025, and Thor must be fully established and connected to the grid by the end of 2027 at the latest.
  • The licence for electricity production is given for 30 years with the possibility of an extension for 5 years.

For further information about the tendering process of Thor Offshore Wind Farm.


News on Thor

You can subscribe to news about Thor by signing up through email to: thor@ens.dk

Contact:

Head of Media Relations, Ture Falbe-Hansen (tfh@ens.dk), phone (+45) 25 13 78 46

Chief Advisor, Jeppe Lundbæk, jel@ens.dk, phone (+45) 3392 7553

Additional links

Contacts

Ture Falbe-Hansen
Head of Press (+45) 2513 7846
Jonas Disager Kraft
Special Advisor (+45) 3395 5038

Related news

Subscribe to the Energy Agency newsletter

Subscribe at Mynewsdesk